Return to Case Studies

North Kesteven School

Facility Management Services - 2015

Facility Management Services required a fully refurbished used modular classroom for North Kesteven School in Lincoln, including foundation, steps and ramps. We visited the grounds to meet with the school's representatives and carried out a full site survey. This led to us discovering some existing foundation from a previous building, which our ground workers were able to partly reuse to minimise the cost to the client.

Following the meeting, it became apparent that Health and safety were paramount, as the install was going to be inside term time. During the refurbishment program, our health and safety pack was submitted and approved before any site works commenced.

The project was handed over on time and on the budget, ready to inspire a new generation.

 

 

×