Return to Case Studies

GB Bio Ltd - Aldborough Gas Plant

Paragon Space - 2017

We were asked by locally based G B Bio to provide for the Aldborough site within a limited budget. The brief was for a 2 storey building to facilitate offices along with a High-Level weighbridge office for the vehicles coming onto their site. Paragon Space had a suitable building in stock and was able to refurbish inside and out to the client’s requirements including Plastisol external finish, UPVC Windows including blinds, full M&E fit-out and external steel staircase with steel gantry on the first floor.  

The building was fully refurbished in our factory in 6 weeks, and site installation took 2 weeks. We are currently in the process of providing them with another building to be used as a Canteen & WC Facility which will be completed shortly.

×